Binghatti Ghost: Handover Date & Completion Status
Binghatti · Al Jadaf · 1,654 units — tracked live against the DLD project registry.
Registry readings over time
All readings (table)
- 24 Sep 2026 FINISHED
- 21 Sep 2026 99% · exp. Mar 2026
- 20 Sep 2026 99% · exp. Mar 2026
- 10 Sep 2026 99% · exp. Mar 2026
- 7 Sep 2026 99% · exp. Mar 2026
- 3 Sep 2026 99% · exp. Mar 2026
- 31 Aug 2026 99% · exp. Mar 2026
- 27 Aug 2026 99% · exp. Mar 2026
- 24 Aug 2026 99% · exp. Mar 2026
- 20 Aug 2026 99% · exp. Mar 2026
- 17 Aug 2026 99% · exp. Mar 2026
- 13 Aug 2026 99% · exp. Mar 2026
- 10 Aug 2026 68% · exp. Mar 2026
- 6 Aug 2026 68% · exp. Mar 2026
- 3 Aug 2026 68% · exp. Mar 2026
- 30 Jul 2026 68% · exp. Mar 2026
- 27 Jul 2026 68% · exp. Mar 2026
- 23 Jul 2026 68% · exp. Mar 2026
- 20 Jul 2026 68% · exp. Mar 2026
- 16 Jul 2026 68% · exp. Mar 2026
- 13 Jul 2026 68% · exp. Mar 2026
- 9 Jul 2026 68% · exp. Mar 2026
- 6 Jul 2026 68% · exp. Mar 2026
- 1 Jul 2026 68% · exp. Mar 2026
- 13 Jun 2026 68% · exp. Mar 2026
Last verified against the DLD registry: 1 Oct 2026 · updated twice weekly
Getting your keys at Binghatti Ghost?
Tell us what you need — snagging inspection, movers, fit-out or a property manager — and we'll connect you with a vetted firm. Free, no markup on your price.
Thank You!
We'll get back to you within 24 hours.
By submitting, you agree we may share these details with the matched vetted firm so they can quote you — nothing more. Privacy Policy
Project facts — DLD registry
- DLD project no.
- 3192
- Registered developer
- Binghatti Developers Fze
- Construction start
- Jul 2024
- Registered project value
- AED 300.0M
- Authority
- Dubai Development Authority (DDA)
- Apartments
- 1,654
Official description: 2B+G+M+2P+20F+R,RESIDENTIAL.The project designed to have a concrete structure and block with internal and external finishes.
Binghatti Ghost in context
Researched & verified editorial — updated 3 Jul 2026
What Is Being Built
Binghatti Ghost is a 20-storey residential tower in Dubai Healthcare City Phase 2, within the Al Jaddaf district. Listed configurations run from studios (roughly 348-654 sq ft) through one, two and three-bedroom units up to about 2,452 sq ft, built around Binghatti's signature crystalline glass facade. The podium includes a retail component, adult and children's pools, a gym, jogging track and covered parking. It is registered as a freehold development, open to foreign ownership.
Al Jaddaf in Practice
Al Jaddaf sits on Dubai Creek and carries a shipbuilding history that is now giving way to mixed-use residential and hospitality development. The Al Jadaf Metro Station (Green Line), operating since 2014, sits a short walk from a marine station offering abra crossings to Dubai Festival City Mall on the opposite bank. The district's defining feature for occupancy purposes is Dubai Healthcare City itself, a cluster of hospitals and clinics next door that anchors a working tenant base of medical staff and administrators, alongside commuters using the Green Line for Downtown and Business Bay access.
Binghatti's Delivery Record
Binghatti, founded in 2008, has delivered more than 60 projects and over 25,000 units across Dubai, and is known for compressed construction schedules, typically 24 to 36 months from launch to handover. Its build-out concentration in Jumeirah Village Circle has been the most visible proof point, with several towers there handed over in the same window. Al Jaddaf carries a second, directly comparable data point: Binghatti Starlight, a 510-unit, 25-storey tower also in Healthcare City Phase 2, is tracking toward Q1 2026 completion — the same quarter cited for Ghost. Two Binghatti towers reaching handover in the same district within the same quarter is a detail worth watching for anyone assessing near-term rental supply in Al Jaddaf specifically, rather than Dubai-wide absorption.
Payment Plan
Per listing data, Binghatti Ghost is sold on a 20/50/30 structure: 20% on booking, 50% spread across construction milestones (tracked in increments through roughly milestone 16), and the remaining 30% due at handover. That weighting front-loads more of the price before completion than a post-handover payment plan would, meaning buyers are expected to have settled 70% of the purchase price by the time keys are issued rather than spreading balance payments after handover.
What Handover Will Mean
Property Finder rental listings for Al Jaddaf currently show studios averaging roughly AED 55,000 a year, one-bedrooms around AED 78,000, and two-bedrooms near AED 110,000, with market commentary placing area yields in the 5-7% band. Those figures predate the added supply from both Ghost and Starlight; whether achieved rents hold up depends on how quickly Healthcare City's tenant demand and Creek-side leasing absorb roughly 1,280 combined units landing in a single district over a similar period. That concentration — not the individual project — is the variable to track into 2026.
What to do now — keys stage
- Snagging before acceptance — inspected first, every defect goes on the developer's list at their cost. Accept first and the leverage flips.
- Book movers before the building's first wave — service-lift slots go fast when hundreds of households arrive in the same month. DEWA, chiller and internet are week-one tasks.
- Investors: service charges accrue on empty units from handover — decide the manager and list in the first-wave window. Compare returns with the STR Income Estimator.
Settling your final payment?
Most Dubai payment plans put the largest instalment at handover. Size your mortgage before the notice arrives.
Before you accept the keys
A snagging inspection before handover puts the defect list on the developer, not on you. Vetted inspectors in our directory.
Browse the DirectoryFrequently asked
When will Binghatti Ghost hand over?
Binghatti Ghost is officially FINISHED in the Dubai Land Department registry — completion was recorded 23 September 2026. Owners should have received (or will shortly receive) their handover notices.
What percentage complete is Binghatti Ghost?
The official DLD registry figure is 100% (FINISHED).
Is Binghatti Ghost delayed?
Binghatti Ghost is FINISHED — no longer pending.
Where does this data come from?
Directly from the Dubai Land Department's public project registry — the escrow-audited construction percentage and official project status, not developer marketing. A project only counts as handed over when its registry status reads FINISHED. See all deliveries on the monthly handover statistics pages.