Binghatti Ghost: Handover Date & Completion Status
Binghatti · Al Jadaf · 785 units — tracked live against the DLD project registry.
Registry readings over time
All readings (table)
- 17 Aug 2026 99% · exp. Mar 2026
- 13 Aug 2026 99% · exp. Mar 2026
- 10 Aug 2026 68% · exp. Mar 2026
- 6 Aug 2026 68% · exp. Mar 2026
- 3 Aug 2026 68% · exp. Mar 2026
- 30 Jul 2026 68% · exp. Mar 2026
- 27 Jul 2026 68% · exp. Mar 2026
- 23 Jul 2026 68% · exp. Mar 2026
- 20 Jul 2026 68% · exp. Mar 2026
- 16 Jul 2026 68% · exp. Mar 2026
- 13 Jul 2026 68% · exp. Mar 2026
- 9 Jul 2026 68% · exp. Mar 2026
- 6 Jul 2026 68% · exp. Mar 2026
- 1 Jul 2026 68% · exp. Mar 2026
- 13 Jun 2026 68% · exp. Mar 2026
Last verified against the DLD registry: 17 Aug 2026 · updated twice weekly
Handover window open
Final payment due at handover? Start the mortgage now
Approvals take 4–8 weeks and pre-approvals last ~60 days — at 99% built, this is the moment. A vetted broker compares 15+ banks, free.
Request received!
We'll connect you with a vetted mortgage broker shortly.
Handover at Binghatti Ghost is coming — line up what you'll need
Snagging inspection, fit-out & furnishing, movers, a handover mortgage, or renting it out — tick what you'll need below and we'll introduce you to a vetted partner at the right moment, free. We'll flag any date slips along the way too.
What will you need at handover?
Tick any — we match you with a vetted partner when the time comes. No cost, no obligation.
No spam — only updates about this building, unsubscribe in one click. Ticking a service above is your permission for us to introduce you to a vetted partner for it (a mortgage broker, snagging inspector…) when your building reaches that stage. Never sold, never shared beyond the services you tick. Privacy Policy
You're watching Binghatti Ghost
We'll email you when the registry reading moves — and the right checklist as handover approaches.
Project facts — DLD registry
- DLD project no.
- 3192
- Registered developer
- Binghatti Developers Fze
- Construction start
- Jul 2024
- Registered project value
- AED 300.0M
- Authority
- Dubai Development Authority (DDA)
- Apartments
- 785
Official description: 2B+G+M+2P+20F+R,RESIDENTIAL.The project designed to have a concrete structure and block with internal and external finishes.
Binghatti Ghost in context
Researched & verified editorial — updated 3 Jul 2026
What Is Being Built
Binghatti Ghost is a 20-storey residential tower in Dubai Healthcare City Phase 2, within the Al Jaddaf district. Listed configurations run from studios (roughly 348-654 sq ft) through one, two and three-bedroom units up to about 2,452 sq ft, built around Binghatti's signature crystalline glass facade. The podium includes a retail component, adult and children's pools, a gym, jogging track and covered parking. It is registered as a freehold development, open to foreign ownership.
Al Jaddaf in Practice
Al Jaddaf sits on Dubai Creek and carries a shipbuilding history that is now giving way to mixed-use residential and hospitality development. The Al Jadaf Metro Station (Green Line), operating since 2014, sits a short walk from a marine station offering abra crossings to Dubai Festival City Mall on the opposite bank. The district's defining feature for occupancy purposes is Dubai Healthcare City itself, a cluster of hospitals and clinics next door that anchors a working tenant base of medical staff and administrators, alongside commuters using the Green Line for Downtown and Business Bay access.
Binghatti's Delivery Record
Binghatti, founded in 2008, has delivered more than 60 projects and over 25,000 units across Dubai, and is known for compressed construction schedules, typically 24 to 36 months from launch to handover. Its build-out concentration in Jumeirah Village Circle has been the most visible proof point, with several towers there handed over in the same window. Al Jaddaf carries a second, directly comparable data point: Binghatti Starlight, a 510-unit, 25-storey tower also in Healthcare City Phase 2, is tracking toward Q1 2026 completion — the same quarter cited for Ghost. Two Binghatti towers reaching handover in the same district within the same quarter is a detail worth watching for anyone assessing near-term rental supply in Al Jaddaf specifically, rather than Dubai-wide absorption.
Payment Plan
Per listing data, Binghatti Ghost is sold on a 20/50/30 structure: 20% on booking, 50% spread across construction milestones (tracked in increments through roughly milestone 16), and the remaining 30% due at handover. That weighting front-loads more of the price before completion than a post-handover payment plan would, meaning buyers are expected to have settled 70% of the purchase price by the time keys are issued rather than spreading balance payments after handover.
What Handover Will Mean
Property Finder rental listings for Al Jaddaf currently show studios averaging roughly AED 55,000 a year, one-bedrooms around AED 78,000, and two-bedrooms near AED 110,000, with market commentary placing area yields in the 5-7% band. Those figures predate the added supply from both Ghost and Starlight; whether achieved rents hold up depends on how quickly Healthcare City's tenant demand and Creek-side leasing absorb roughly 1,280 combined units landing in a single district over a similar period. That concentration — not the individual project — is the variable to track into 2026.
What to do now — handover approaching (99%)
- Start the mortgage now — approvals take 4–8 weeks, pre-approvals last ~60 days, and at 99% the notice window is close. Talk to a vetted broker above.
- Book the snagging inspection before you sign acceptance — AED 1,000–2,500 for most apartments, arranged in days via the directory.
- Budget the cash-only items: 4% DLD transfer, 0.25% mortgage registration, trustee & valuation, first year's service charges — calculate them.
Final payment due at handover?
Most Dubai payment plans put the largest instalment at handover. Size your mortgage before the notice arrives.
Before you accept the keys
A snagging inspection before handover puts the defect list on the developer, not on you. Vetted inspectors in our directory.
Browse the DirectoryFrequently asked
When will Binghatti Ghost hand over?
Binghatti Ghost is at 99% in the DLD registry — structurally complete and in the handover stage. Owners can expect the official DLD completion and handover notices shortly.
What percentage complete is Binghatti Ghost?
The official DLD registry figure is 99%. This is the escrow-audited construction percentage, not a marketing estimate.
Is Binghatti Ghost delayed?
Binghatti Ghost is structurally complete (~100%); handover is imminent, whatever the original date said.
Where does this data come from?
Directly from the Dubai Land Department's public project registry — the escrow-audited construction percentage and official project status, not developer marketing. A project only counts as handed over when its registry status reads FINISHED. See all deliveries on the monthly handover statistics pages.