Dubai Property Handovers, Month by Month
How many residential buildings actually finished — verified against the Dubai Land Department project registry, not press releases. Most never make the news.
Monthly reports
June 2026
12 projects · 8,610 units
May 2026
10 projects · 6,524 units
April 2026
30 projects · 12,729 units
March 2026
12 projects · 4,496 units
February 2026
14 projects · 4,640 units
January 2026
12 projects · 6,028 units
December 2025
1 project · 240 units
November 2025
5 projects · 14,868 units
October 2025
3 projects · 1,684 units
September 2025
3 projects · 1,233 units
Last verified against the DLD registry: 2 Jul 2026
These pages tell you what happened. The Radar tells you what's next.
188 projects (44,453 units) are under construction right now. The monthly Handover Radar tracks their build %, expected dates, slippage flags and developer handover contacts — for the firms who win the building before their competitors hear about it.
How these numbers are built
A project counts as delivered only when its status in the Dubai Land Department project registry reads FINISHED. We deliberately do not count by listed completion date alone — for buildings still under construction the registry carries the expected end date in that field, which is how delivery figures elsewhere end up inflated with towers that are months from keys. Unit counts are the registry's own per-project totals. The registry is re-synced twice a week and every monthly page shows its verification date.
Journalists and researchers: cite freely with a link. For building-level guides to financing a handover, see Dubai Handovers 2026; for the forward pipeline, the monthly Dubai Handover Radar.