DLD Registry Data

Dubai Property Handovers: April 2026

Every residential project that actually finished in April 2026 — verified against the Dubai Land Department project registry, not press releases.

30
projects delivered
12,729
homes handed over
27,893
units YTD (68 projects)

vs March 2026: 12 projects / 4,496 units (+8,233 units) · see March 2026

Last verified against the DLD registry: 2 Jul 2026

In April 2026, 30 residential projects totalling 12,729 units reached FINISHED status in the Dubai Land Department project registry, led by Al Barsha South Fourth.

The largest delivery was Sobha Hartland - Crest Grande by Sobha in Al Merkadh — 2,364 units handed over on 15 April. That put the month 8,233 units ahead of March 2026.

Source: DLD project registry via Real Estate Club Dubai — cite freely with a link to this page.

Buildings delivered in April 2026

Project Developer Area Units Completed
Sobha Hartland - Crest Grande Sobha Al Merkadh 2,364 15 Apr
Binghatti Apex Binghatti Al Barsha South Fourth 1,230 23 Apr
The Fields At D11 - Mbrmc G&Co Real Estate Dev Wadi Al Safa 3 1,028 10 Apr
Regalia Deyaar Business Bay 921 29 Apr
Serenia Living Palma Homes Real Est Palm Jumeirah 844 23 Apr
Nas3 Rabdan Real Estate D Al Barshaa South Third 588 8 Apr
Damac Lagoons - Costa Brava (1) Island Oasis Propert Al Hebiah Fifth 555 10 Apr
The Haven Garden Metrical Real Estate Al Barsha South Fourth 415 6 Apr
Ab Cavalier Ab Developers Al Barsha South Fourth 379 23 Apr
Damac Lagoons - Malta (2) Island Oasis Propert Al Hebiah Fifth 367 8 Apr
Arbor View E L P D Developers Al Barshaa South Third 361 6 Apr
Pearl House Iii By Imtiaz Imtiaz Ghd Real Esta Al Barsha South Fourth 356 26 Apr
Koro One Koro Real Estate Dev Al Satwa 317 24 Apr
Vista By Prestige One Prestige One Luxury Al Hebiah Fourth 302 2 Apr
Jebel Ali Village Townhouses- Phase 1 Jebel Ali Village Jabal Ali First 286 29 Apr
Olivo Park Residences By Evera Evera Real Estate De Al Barsha South Fourth 284 28 Apr
Jebel Ali Village Jebel Ali Village Jabal Ali First 281 29 Apr
Marquis Galleria Marquis Home Develop Al Barshaa South Third 254 10 Apr
Aark Residences Aark Developers Wadi Al Safa 5 200 27 Apr
Jebel Ali Village Townhouses - Phase 3 Jebel Ali Village Jabal Ali First 198 29 Apr
Cresswell Residences Abdulwahed Faqeeh Pr Madinat Al Mataar 166 20 Apr
Waha Living By Al Yakka Alyakka Developers Al Satwa 158 7 Apr
The Valley - Farm Gardens Emaar Al Yufrah 1 146 6 Apr
Volna By Kasco Kasco Real Estate De Al Jadaf 141 22 Apr
Divine Residencia Takmeel Real Estate Al Hebiah Second 139 20 Apr
Jebel Ali Village Townhouses - Phase 2 Jebel Ali Village Jabal Ali First 133 29 Apr
Haven Living Metac Properties Palm Deira 126 28 Apr
Damac Lagoons - Santorini (3) Island Oasis Propert Al Hebiah Fifth 96 9 Apr
Azizi Riviera 56 Azizi Al Merkadh 82 29 Apr
The Veranda Collection 1 Pacifique Global Pro Al Barsha South Fourth 12 16 Apr

Top developers by delivered units

  • Sobha (1 project) 2,364
  • Binghatti (1 project) 1,230
  • G&Co Real Estate Dev (1 project) 1,028
  • Island Oasis Propert (3 projects) 1,018
  • Deyaar (1 project) 921
  • Jebel Ali Village (4 projects) 898

Where the keys landed

  • Al Barsha South Fourth 2,676
  • Al Merkadh 2,446
  • Al Barshaa South Third 1,203
  • Wadi Al Safa 3 1,028
  • Al Hebiah Fifth 1,018
  • Business Bay 921

Need next month before it happens?

The Handover Radar tracks 188 projects still under construction — build %, expected dates, slippage flags and developer handover contacts. Published monthly.

Explore the Radar

How these numbers are built

A project counts as delivered only when its status in the Dubai Land Department project registry reads FINISHED. We deliberately do not count projects by their listed completion date alone — for buildings still under construction the registry carries the expected end date in that field, which is how "delivered units" figures elsewhere end up inflated with towers that are months from keys. Unit counts are the registry's own totals per project. Figures are re-verified on every sync (last: 2 Jul 2026).

Cite freely with a link to this page. For the forward pipeline — what's about to hand over, at what build percentage, and which "Q3" promises will actually slip — see the monthly Dubai Handover Radar.