Behind schedule — 46%

Binghatti Ruby: Handover Date & Completion Status

Binghatti · Al Barsha South Fourth · 628 units — tracked live against the DLD project registry.

46%
official build progress
Overdue
February 2026
original DLD estimate · 5 months past due
628
units
Construction progress 46%

Registry readings over time

13 Jun 2026: 20% · exp. Feb 2026 20% 13 Jun 1 Jul 2026: 20% · exp. Feb 2026 6 Jul 2026: 20% · exp. Feb 2026 9 Jul 2026: 20% · exp. Feb 2026 13 Jul 2026: 20% · exp. Feb 2026 16 Jul 2026: 20% · exp. Feb 2026 20 Jul 2026: 20% · exp. Feb 2026 23 Jul 2026: 20% · exp. Feb 2026 27 Jul 2026: 20% · exp. Feb 2026 30 Jul 2026: 46% · exp. Feb 2026 3 Aug 2026: 46% · exp. Feb 2026 6 Aug 2026: 46% · exp. Feb 2026 10 Aug 2026: 46% · exp. Feb 2026 13 Aug 2026: 46% · exp. Feb 2026 17 Aug 2026: 46% · exp. Feb 2026 46% 17 Aug
All readings (table)
  • 17 Aug 2026 46% · exp. Feb 2026
  • 13 Aug 2026 46% · exp. Feb 2026
  • 10 Aug 2026 46% · exp. Feb 2026
  • 6 Aug 2026 46% · exp. Feb 2026
  • 3 Aug 2026 46% · exp. Feb 2026
  • 30 Jul 2026 46% · exp. Feb 2026
  • 27 Jul 2026 20% · exp. Feb 2026
  • 23 Jul 2026 20% · exp. Feb 2026
  • 20 Jul 2026 20% · exp. Feb 2026
  • 16 Jul 2026 20% · exp. Feb 2026
  • 13 Jul 2026 20% · exp. Feb 2026
  • 9 Jul 2026 20% · exp. Feb 2026
  • 6 Jul 2026 20% · exp. Feb 2026
  • 1 Jul 2026 20% · exp. Feb 2026
  • 13 Jun 2026 20% · exp. Feb 2026

Last verified against the DLD registry: 17 Aug 2026 · updated twice weekly

Project facts — DLD registry

DLD project no.
3533
Registered developer
Binghatti Developers Fze
Construction start
Jan 2025
Registered project value
AED 220.2M
Authority
Trakhees
Apartments
628

Official description: UB+B + G + 4P +2 Office+ 18 RESIDENTIAL FLOORS + ROOF

Binghatti Ruby in context

Researched & verified editorial — updated 3 Jul 2026

What Binghatti Is Building at JVC District 16

Binghatti Ruby is a mixed-use high-rise on Jumeirah Village Circle's District 16, combining 18 residential floors with four parking levels and dedicated office and retail floors below street level. Broker documentation tied to the project's floor plans lists 572 apartments — weighted toward one-bedroom layouts (185 units) and two-bedroom units (66), with only two three-bedroom units — alongside 45 standalone office suites, putting total sellable inventory in the tower at roughly 617 units. That studio-to-two-bed skew, with three-bedroom stock kept deliberately scarce, matches the unit mix Binghatti has repeated across its other JVC towers. Interiors are marketed as unfurnished, with marble and timber-effect finishes cited in developer materials, and the building includes an infinity pool and a separate deck-level pool rather than a single shared amenity floor.

Ruby's Place in the Gem Series

Ruby extends Binghatti's recurring gemstone-naming convention in JVC, following Emerald (District 15, 22 storeys, completed February 2024) and Amber (District 11, 24 storeys, completed December 2024), both now handed over and trading as completed stock on the resale and rental market. Onyx, a taller 36-floor tower elsewhere in the community, is also listed as delivered. At 18 residential floors, Ruby is the most modest in scale of the delivered or near-delivery towers in the series, and its District 16 address places it apart from where Emerald and Amber landed — new supply here lands in a different micro-pocket of JVC rather than stacking directly against those two buildings' immediate blocks.

Payment Structure

Binghatti's own project page and Property Finder's listing both cite a 20/50/30 structure: 20% on booking, 50% staged through construction, and the remaining 30% due on handover. That back-loaded 30% at completion is a heavier handover obligation than the 10-20% terms common on some competing JVC launches, a detail worth factoring into cash-flow planning ahead of the Q1 2026 completion window. Buyers relying on rental income to cover that final tranche should note it falls due at, not after, handover — there is no grace period built into the structure as advertised.

What Handover Will Test

When Ruby's roughly 570-plus apartments reach handover, they will be leasing into a District 16 market that has already cooled by some measures: Bayut's data puts the average achieved rent for District 16 apartments at AED 74,712 a year, with asking rents down 7% over the prior six months even as the district-wide listed average sat higher, near AED 76,575. That is the specific pocket of JVC where Ruby's studios and one-bedrooms will be priced, distinct from JVC's broader average — landlords bringing this tower's units to market will be competing in a district where rents were softening before this supply had even cleared handover. Whether that trend holds through Q1 2026 will depend partly on how much of Ruby's own inventory lands with investors intent on leasing rather than owner-occupiers, a split the project has not published.

What to do now — early construction (46%)

  • Keep instalments strictly to the payment plan and confirm every payment lands in the project's escrow account — never a personal account.
  • Model your handover cash-out early: final instalment + 4% DLD fee + costs — the DLD Fee Calculator does the math.
  • Watch this page — expected dates at this stage move often, and we'll email you when the registry reading changes.

Final payment due at handover?

Most Dubai payment plans put the largest instalment at handover. Size your mortgage before the notice arrives.

Before you accept the keys

A snagging inspection before handover puts the defect list on the developer, not on you. Vetted inspectors in our directory.

Browse the Directory

Frequently asked

When will Binghatti Ruby hand over?

The DLD registry lists Binghatti Ruby at 46% construction, now past its original registry estimate of February 2026. It is behind that date — realistic handover is later. This page re-verifies twice a week.

What percentage complete is Binghatti Ruby?

The official DLD registry figure is 46%. This is the escrow-audited construction percentage, not a marketing estimate.

Is Binghatti Ruby delayed?

Yes — Binghatti Ruby is past its original DLD estimate of February 2026 and still at 46% construction, so handover will land later than the registry's original date.

Where does this data come from?

Directly from the Dubai Land Department's public project registry — the escrow-audited construction percentage and official project status, not developer marketing. A project only counts as handed over when its registry status reads FINISHED. See all deliveries on the monthly handover statistics pages.