Mudon Al Ranim 7: Handover Date & Completion Status

Mdn Real Estate · Al Hebiah Sixth · 248 units — tracked live against the DLD project registry.

100%
official build progress
September 2026
completed
248
units
Construction progress 100%

Registry readings over time

13 Jun 2026: 92% · exp. Sep 2026 92% 13 Jun 1 Jul 2026: 92% · exp. Sep 2026 2 Jul 2026: 92% · exp. Sep 2026 6 Jul 2026: 92% · exp. Sep 2026 9 Jul 2026: 92% · exp. Sep 2026 13 Jul 2026: 92% · exp. Sep 2026 16 Jul 2026: 92% · exp. Sep 2026 20 Jul 2026: 92% · exp. Sep 2026 23 Jul 2026: 92% · exp. Sep 2026 27 Jul 2026: 92% · exp. Sep 2026 30 Jul 2026: 92% · exp. Sep 2026 3 Aug 2026: 92% · exp. Sep 2026 6 Aug 2026: 92% · exp. Sep 2026 10 Aug 2026: 92% · exp. Sep 2026 13 Aug 2026: 92% · exp. Sep 2026 17 Aug 2026: 92% · exp. Sep 2026 20 Aug 2026: 92% · exp. Sep 2026 24 Aug 2026: 92% · exp. Sep 2026 27 Aug 2026: 92% · exp. Sep 2026 31 Aug 2026: 92% · exp. Sep 2026 3 Sep 2026: 92% · exp. Sep 2026 7 Sep 2026: 92% · exp. Sep 2026 10 Sep 2026: 92% · exp. Sep 2026 20 Sep 2026: FINISHED FINISHED 20 Sep
All readings (table)
  • 20 Sep 2026 FINISHED
  • 10 Sep 2026 92% · exp. Sep 2026
  • 7 Sep 2026 92% · exp. Sep 2026
  • 3 Sep 2026 92% · exp. Sep 2026
  • 31 Aug 2026 92% · exp. Sep 2026
  • 27 Aug 2026 92% · exp. Sep 2026
  • 24 Aug 2026 92% · exp. Sep 2026
  • 20 Aug 2026 92% · exp. Sep 2026
  • 17 Aug 2026 92% · exp. Sep 2026
  • 13 Aug 2026 92% · exp. Sep 2026
  • 10 Aug 2026 92% · exp. Sep 2026
  • 6 Aug 2026 92% · exp. Sep 2026
  • 3 Aug 2026 92% · exp. Sep 2026
  • 30 Jul 2026 92% · exp. Sep 2026
  • 27 Jul 2026 92% · exp. Sep 2026
  • 23 Jul 2026 92% · exp. Sep 2026
  • 20 Jul 2026 92% · exp. Sep 2026
  • 16 Jul 2026 92% · exp. Sep 2026
  • 13 Jul 2026 92% · exp. Sep 2026
  • 9 Jul 2026 92% · exp. Sep 2026
  • 6 Jul 2026 92% · exp. Sep 2026
  • 2 Jul 2026 92% · exp. Sep 2026
  • 1 Jul 2026 92% · exp. Sep 2026
  • 13 Jun 2026 92% · exp. Sep 2026

Last verified against the DLD registry: 1 Oct 2026 · updated twice weekly

Getting your keys at Mudon Al Ranim 7?

Tell us what you need — snagging inspection, movers, fit-out or a property manager — and we'll connect you with a vetted firm. Free, no markup on your price.

Something went wrong. Please try again.

Thank You!

We'll get back to you within 24 hours.

By submitting, you agree we may share these details with the matched vetted firm so they can quote you — nothing more. Privacy Policy

Project facts — DLD registry

DLD project no.
2699
Registered developer
Mdn Real Estate L.l.c
Construction start
Sep 2023
Registered project value
AED 283.9M
Authority
Dubai Development Authority (DDA)
Villas
248

Official description: 49 plots for a total of 248 units (No.of G+1 = 178, No.of G+2 = 70 ) Townhouses -mix of 4 bed and 3 bed units, attached in groups of 4 and 6 units.

Mudon Al Ranim 7 in context

Researched & verified editorial — updated 3 Jul 2026

The Al Ranim Sequence, Phase by Phase

Mudon Al Ranim is not a single project but a rolling sequence of townhouse releases that Dubai Properties began launching inside Mudon in the second quarter of 2022. Phase 1 and Phase 2 reached handover in the fourth quarter of 2025, Phase 3 followed in the first quarter of 2026, and Phase 5 is scheduled for July 2026 - a cadence of deliveries landing every few months since late 2025. Phase 7 sits toward the back of the eight-phase run, alongside Phase 8, with both tracking toward September 2026 completion. For buyers who bought off-plan in 2022 and 2023, that means Al Ranim has effectively been handing over in installments for close to a year already by the time Phase 7 closes - giving its owners a working precedent in contractors, snagging processes and community services to reference from the phases that came before it.

Mudon on the Ground, Not on the Brochure

By the time Phase 7 changes hands, Mudon will be roughly a decade into operating as a community rather than a fresh master plan. Two schools sit inside the gates - Jebel Ali School, teaching the British curriculum, and Fairgreen International School, an IB campus - with GEMS Metropole School and South View School a short drive away and Blossom Mudon Nursery covering early years. Ash Mount School, a full IB campus for ages 3 to 18, is due to open in the wider Dubailand area in August 2026, roughly matching the Phase 7 handover window. The community's shared green space, Mudon Central Park, covers close to 1.8 million square feet of jogging and cycling tracks, outdoor gym equipment, a dog park and event lawns - infrastructure that predates Al Ranim and does not depend on any single phase's completion. That maturity shapes the tenant profile buyers should expect: Mudon has settled into a stroller-and-school-run market, where townhouse demand tracks family relocation cycles around the August-September school year more closely than the investor-driven churn seen in newer off-plan clusters elsewhere in Dubailand.

What the Handover Checklist Should Actually Cover

For owners approaching a Q3 2026 handover, the practical checklist is narrower than the marketing material suggests. Snagging on a townhouse means checking party walls and rear-garden drainage as closely as interior finish quality - a Mudon-specific concern given how tightly adjoining plots sit across the Al Ranim phases. DEWA connection timing, the community service charge schedule, and the developer's defects liability period are worth confirming in writing before the final payment is released, not after moving in. Buyers relying on the final handover installment - the standard structure used across recent Al Ranim releases - should also pin down the exact trigger for that payment, since the gap between a unit completion certificate and a live DEWA connection has been a recurring friction point on other Dubai Properties handovers. None of this shows up in a floor plan, but it is what determines whether a Phase 7 handover is a smooth transition or a drawn-out one.

What to do now — keys stage

  • Snagging before acceptance — inspected first, every defect goes on the developer's list at their cost. Accept first and the leverage flips.
  • Book movers before the building's first wave — service-lift slots go fast when hundreds of households arrive in the same month. DEWA, chiller and internet are week-one tasks.
  • Investors: service charges accrue on empty units from handover — decide the manager and list in the first-wave window. Compare returns with the STR Income Estimator.

Settling your final payment?

Most Dubai payment plans put the largest instalment at handover. Size your mortgage before the notice arrives.

Before you accept the keys

A snagging inspection before handover puts the defect list on the developer, not on you. Vetted inspectors in our directory.

Browse the Directory

Frequently asked

When will Mudon Al Ranim 7 hand over?

Mudon Al Ranim 7 is officially FINISHED in the Dubai Land Department registry — completion was recorded 17 September 2026. Owners should have received (or will shortly receive) their handover notices.

What percentage complete is Mudon Al Ranim 7?

The official DLD registry figure is 100% (FINISHED).

Is Mudon Al Ranim 7 delayed?

Mudon Al Ranim 7 is FINISHED — no longer pending.

Where does this data come from?

Directly from the Dubai Land Department's public project registry — the escrow-audited construction percentage and official project status, not developer marketing. A project only counts as handed over when its registry status reads FINISHED. See all deliveries on the monthly handover statistics pages.

Also tracking in Al Hebiah Sixth