Mudon Al Ranim 7: Handover Date & Completion Status
Mdn Real Estate · Al Hebiah Sixth · 248 units — tracked live against the DLD project registry.
Registry readings
- 17 Aug 2026 92% · exp. Sep 2026
- 13 Aug 2026 92% · exp. Sep 2026
- 10 Aug 2026 92% · exp. Sep 2026
- 6 Aug 2026 92% · exp. Sep 2026
- 3 Aug 2026 92% · exp. Sep 2026
- 30 Jul 2026 92% · exp. Sep 2026
The progress chart appears here once the registry reading starts moving.
Last verified against the DLD registry: 17 Aug 2026 · updated twice weekly
Handover window open
Final payment due at handover? Start the mortgage now
Approvals take 4–8 weeks and pre-approvals last ~60 days — at 92% built, this is the moment. A vetted broker compares 15+ banks, free.
Request received!
We'll connect you with a vetted mortgage broker shortly.
Handover at Mudon Al Ranim 7 is coming — line up what you'll need
Snagging inspection, fit-out & furnishing, movers, a handover mortgage, or renting it out — tick what you'll need below and we'll introduce you to a vetted partner at the right moment, free. We'll flag any date slips along the way too.
What will you need at handover?
Tick any — we match you with a vetted partner when the time comes. No cost, no obligation.
No spam — only updates about this building, unsubscribe in one click. Ticking a service above is your permission for us to introduce you to a vetted partner for it (a mortgage broker, snagging inspector…) when your building reaches that stage. Never sold, never shared beyond the services you tick. Privacy Policy
You're watching Mudon Al Ranim 7
We'll email you when the registry reading moves — and the right checklist as handover approaches.
Project facts — DLD registry
- DLD project no.
- 2699
- Registered developer
- Mdn Real Estate L.l.c
- Construction start
- Sep 2023
- Registered project value
- AED 283.9M
- Authority
- Dubai Development Authority (DDA)
- Villas
- 248
Official description: 49 plots for a total of 248 units (No.of G+1 = 178, No.of G+2 = 70 ) Townhouses -mix of 4 bed and 3 bed units, attached in groups of 4 and 6 units.
Mudon Al Ranim 7 in context
Researched & verified editorial — updated 3 Jul 2026
The Al Ranim Sequence, Phase by Phase
Mudon Al Ranim is not a single project but a rolling sequence of townhouse releases that Dubai Properties began launching inside Mudon in the second quarter of 2022. Phase 1 and Phase 2 reached handover in the fourth quarter of 2025, Phase 3 followed in the first quarter of 2026, and Phase 5 is scheduled for July 2026 - a cadence of deliveries landing every few months since late 2025. Phase 7 sits toward the back of the eight-phase run, alongside Phase 8, with both tracking toward September 2026 completion. For buyers who bought off-plan in 2022 and 2023, that means Al Ranim has effectively been handing over in installments for close to a year already by the time Phase 7 closes - giving its owners a working precedent in contractors, snagging processes and community services to reference from the phases that came before it.
Mudon on the Ground, Not on the Brochure
By the time Phase 7 changes hands, Mudon will be roughly a decade into operating as a community rather than a fresh master plan. Two schools sit inside the gates - Jebel Ali School, teaching the British curriculum, and Fairgreen International School, an IB campus - with GEMS Metropole School and South View School a short drive away and Blossom Mudon Nursery covering early years. Ash Mount School, a full IB campus for ages 3 to 18, is due to open in the wider Dubailand area in August 2026, roughly matching the Phase 7 handover window. The community's shared green space, Mudon Central Park, covers close to 1.8 million square feet of jogging and cycling tracks, outdoor gym equipment, a dog park and event lawns - infrastructure that predates Al Ranim and does not depend on any single phase's completion. That maturity shapes the tenant profile buyers should expect: Mudon has settled into a stroller-and-school-run market, where townhouse demand tracks family relocation cycles around the August-September school year more closely than the investor-driven churn seen in newer off-plan clusters elsewhere in Dubailand.
What the Handover Checklist Should Actually Cover
For owners approaching a Q3 2026 handover, the practical checklist is narrower than the marketing material suggests. Snagging on a townhouse means checking party walls and rear-garden drainage as closely as interior finish quality - a Mudon-specific concern given how tightly adjoining plots sit across the Al Ranim phases. DEWA connection timing, the community service charge schedule, and the developer's defects liability period are worth confirming in writing before the final payment is released, not after moving in. Buyers relying on the final handover installment - the standard structure used across recent Al Ranim releases - should also pin down the exact trigger for that payment, since the gap between a unit completion certificate and a live DEWA connection has been a recurring friction point on other Dubai Properties handovers. None of this shows up in a floor plan, but it is what determines whether a Phase 7 handover is a smooth transition or a drawn-out one.
What to do now — handover approaching (92%)
- Start the mortgage now — approvals take 4–8 weeks, pre-approvals last ~60 days, and at 92% the notice window is close. Talk to a vetted broker above.
- Book the snagging inspection before you sign acceptance — AED 1,000–2,500 for most apartments, arranged in days via the directory.
- Budget the cash-only items: 4% DLD transfer, 0.25% mortgage registration, trustee & valuation, first year's service charges — calculate them.
Final payment due at handover?
Most Dubai payment plans put the largest instalment at handover. Size your mortgage before the notice arrives.
Before you accept the keys
A snagging inspection before handover puts the defect list on the developer, not on you. Vetted inspectors in our directory.
Browse the DirectoryFrequently asked
When will Mudon Al Ranim 7 hand over?
The DLD registry lists Mudon Al Ranim 7 at 92% construction with an expected date of September 2026 — the registry's own estimate, which routinely slips. This page re-verifies twice a week.
What percentage complete is Mudon Al Ranim 7?
The official DLD registry figure is 92%. This is the escrow-audited construction percentage, not a marketing estimate.
Is Mudon Al Ranim 7 delayed?
It is on the registry's timeline so far — no material slippage recorded since we started tracking. Bear in mind DLD dates are optimistic and can still move.
Where does this data come from?
Directly from the Dubai Land Department's public project registry — the escrow-audited construction percentage and official project status, not developer marketing. A project only counts as handed over when its registry status reads FINISHED. See all deliveries on the monthly handover statistics pages.