Under construction — 96%

Nad Al Sheba Gardens Phase 3: Handover Date & Completion Status

Al Qudra Estates · Nad Al Shiba First · 235 units — tracked live against the DLD project registry.

96%
official build progress
April 2026
expected completion
235
units
Construction progress 96%

Registry readings

  • 1 Jul 2026 96% · exp. Apr 2026
  • 13 Jun 2026 96% · exp. Apr 2026

The progress chart appears here once the registry reading starts moving.

Last verified against the DLD registry: 2 Jul 2026 · updated twice weekly

Handover window open

Final payment due at handover? Start the mortgage now

Approvals take 4–8 weeks and pre-approvals last ~60 days — at 96% built, this is the moment. A vetted broker compares 15+ banks, free.

Something went wrong. Please try again.

No obligation. We never share your details without your say-so.

Request received!

We'll connect you with a vetted mortgage broker shortly.

Project facts — DLD registry

DLD project no.
2484
Registered developer
Al Qudra Estates L.l.c
Construction start
Jan 2023
Registered project value
AED 619.2M
Authority
Dubai Development Authority (DDA)
Villas
235

Official description: G+1 & G+2 x 235 Villas+Townhouses,The project designed to have a concrete structure and block with internal and external finishes.

What to do now — handover approaching (96%)

  • Start the mortgage now — approvals take 4–8 weeks, pre-approvals last ~60 days, and at 96% the notice window is close. Talk to a vetted broker above.
  • Book the snagging inspection before you sign acceptance — AED 1,000–2,500 for most apartments, arranged in days via the directory.
  • Budget the cash-only items: 4% DLD transfer, 0.25% mortgage registration, trustee & valuation, first year's service charges — calculate them.

Final payment due at handover?

Most Dubai payment plans put the largest instalment at handover. Size your mortgage before the notice arrives.

Before you accept the keys

A snagging inspection before handover puts the defect list on the developer, not on you. Vetted inspectors in our directory.

Browse the Directory

Frequently asked

When will Nad Al Sheba Gardens Phase 3 hand over?

The DLD registry currently lists Nad Al Sheba Gardens Phase 3 at 96% construction with an expected end date of April 2026. Expected dates can slip — this page re-verifies against the registry twice a week.

What percentage complete is Nad Al Sheba Gardens Phase 3?

The official DLD registry figure is 96%. This is the escrow-audited construction percentage, not a marketing estimate.

Is Nad Al Sheba Gardens Phase 3 delayed?

No material slippage recorded since we started tracking — the expected date has held within a month.

Where does this data come from?

Directly from the Dubai Land Department's public project registry — the escrow-audited construction percentage and official project status, not developer marketing. A project only counts as handed over when its registry status reads FINISHED. See all deliveries on the monthly handover statistics pages.